At Site A the ground floor through 13th floor commercial and 16th floor Residential slabs are complete. The commercial 14 &15 and residential 17, 18 and 19th floor slabs will be complete by 10/26 . There will be water, sewer and finalizing of Con-Ed work on Kent avenue during the following few weeks. Sidewalk shed is erected. MEP trades will continue their overhead and in deck work. Precast Facade erection has begun on a second shift and will end prior to 10pm every evening. The facade will be complete on the residential tower up to the 11th floor by the end of October.
Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.
The public park located on Site C is open 6 days a week.
Site E construction is complete.