DOMINO CONSTRUCTION UPDATE: Weeks of October 29th and November 5th, 2018
At Site A the ground floor through 15th floor commercial and 20th floor Residential slabs are complete. The commercial 16, 17 & 18 and residential 21, 22 and 23rd floor slabs will be complete by 11/9 . There will be … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE: Weeks of October 29th and November 5th, 2018