At Site A the ground floor through 15th floor commercial and 20th floor Residential slabs are complete. The commercial 16, 17 & 18 and residential 21, 22 and 23rd floor slabs will be complete by 11/9 . There will be water, sewer and finalizing of Con-Ed work on Kent avenue during the following few weeks. Sidewalk shed is erected. MEP trades will continue their overhead and in deck work. Precast Facade erection has begun on a second shift and will end prior to 10pm every evening. The facade will be complete on the residential tower up to the 11th floor by the end of October and then will continue up the building on the interior of the “O” in the building.
Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.
The public park located on Site C is open 6 days a week.
Site E construction is complete.