Monthly Archives: February 2019

DOMINO CONSTRUCTION UPDATE: Weeks of February 4th and February 11th, 2019

At Site A the ground floor through 28th floor slabs are complete. We will be pouring the 29th & 30th floor slab during these weeks. We have schedule a crane jump for the 9th and 10th. MEP trades will continue … Continue reading

Posted in Construction Updates | Comments Off on DOMINO CONSTRUCTION UPDATE: Weeks of February 4th and February 11th, 2019