DOMINO CONSTRUCTION UPDATE: Weeks of March 18th and March 25th, 2019
At Site A the ground floor through 35rd floor slabs are complete. We will be pouring the 36th , 37th & 38th floor slab during these weeks. Topping out of the building is scheduled for the end of April. MEP trades … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE: Weeks of March 18th and March 25th, 2019