Daily Archives: November 15, 2019

DOMINO CONSTRUCTION UPDATE: Weeks of November 18th and November 25th, 2019

At Site A the ground floor through 42nd floor slabs are complete. The bulkheads for the building are complete. MEP trades will continue fit out work. Precast Facade erection is complete, except for the commercial hoist area of the commercial … Continue reading