DOMINO CONSTRUCTION UPDATE: Weeks of October 26th& November 2nd
Site A completed. Retail tenant fit outs on going and Office Tenant fit outs TBD. Refinery shoring and demolition work is complete; this consists of exterior steel structures to brace the existing façade. Shoring to remain in place. Foundation and … Continue reading