DOMINO CONSTRUCTION UPDATE: Weeks of November 23rd & November 30th
Refinery shoring and demolition work is complete; this consists of exterior steel structures to brace the existing façade. Shoring to remain in place. Foundation and SOE work are ongoing. Exterior Masonry restoration work is underway. Tower Crane has been erected … Continue reading