DOMINO CONSTRUCTION UPDATE- WEEKS OF NOVEMBER 29 and DECEMBER 6 2021
Refinery temporary shoring and demolition phases of work are now complete; consisting of exterior steel structures to brace the existing façade. Steel shoring to remain in place during construction. Exterior Masonry restoration work is underway. Tower Crane has been erected … Continue reading
Posted in Construction Updates