DOMINO CONSTRUCTION UPDATE- WEEKS OF JANUARY 10 and JANUARY 17 2022

Refinery temporary shoring and demolition phases of work are now complete; consisting of exterior steel structures to brace the existing façade. Steel shoring to remain in place during construction. Exterior Masonry restoration work is underway. Tower Crane has been erected and is active on a daily basis. Concrete superstructure and Steel Erection has commenced.

Site B is fenced off and is used for refinery construction staging.

Construction of Domino Park is complete. The entrances are on Grand St, South 5th St, and South 4th St.

Site C is closed to the public.