DOMINO CONSTRUCTION UPDATE- WEEKS OF MAY 30 AND JUNE 6 2022
Refinery temporary shoring and demolition phases of work are now complete;consisting of exterior steel structures to brace the existing façade. Steelshoring to remain in place during construction. Exterior Masonry restorationwork is underway. Tower Crane has been erected and is active … Continue reading