-
Recent Posts
- DOMINO CONSTRUCTION UPDATE- WEEKS OF DECEMBER 8 AND DECEMBER 15
- DOMINO CONSTRUCTION UPDATE- WEEKS OF NOVEMBER 24 AND DECEMBER 1
- DOMINO CONSTRUCTION UPDATE- WEEKS OF NOVEMBER 10 AND NOVEMBER 17
- DOMINO CONSTRUCTION UPDATE- WEEKS OF OCTOBER 27 AND NOVEMBER 3
- DOMINO CONSTRUCTION UPDATE- WEEKS OF OCTOBER 13 AND OCTOBER 20
DOMINO CONSTRUCTION UPDATE- WEEKS OF MAY 2 AND 9 2022
Refinery temporary shoring and demolition phases of work are now complete;
consisting of exterior steel structures to brace the existing façade. Steel
shoring to remain in place during construction. Exterior Masonry restoration
work is underway. Tower Crane has been erected and is active on a daily basis.
Concrete superstructure and Steel Erection has commenced.
Site B is fenced off and is used for refinery construction staging. A separate portion of site B is accessible off river street containing Domino Park bathrooms and staffing/operations.
Construction of Domino Park is complete. The entrances are on Grand St,
South 1st St, and South 5th St.
Sites C and D have begun excavation- with ongoing deep foundation work using drill rigs.
This entry was posted in Construction Updates. Bookmark the permalink.