-
Recent Posts
- DOMINO CONSTRUCTION UPDATE- WEEKS OF FEBRUARY 16 AND FEBRUARY 23
- DOMINO CONSTRUCTION UPDATE- WEEKS OF FEBRUARY 2 AND FEBRUARY 9
- DOMINO CONSTRUCTION UPDATE- WEEKS OF JANUARY 19 AND JANUARY 26
- DOMINO CONSTRUCTION UPDATE- WEEKS OF JANUARY 5 AND JANUARY 12
- DOMINO CONSTRUCTION UPDATE- WEEKS OF DECEMBER 22 AND DECEMBER 29
Monthly Archives: June 2022
DOMINO CONSTRUCTION UPDATE- WEEKS OF MAY 2 AND 9 2022
Refinery temporary shoring and demolition phases of work are now complete; consisting of exterior steel structures to brace the existing façade. Steel shoring to remain in place during construction. Exterior Masonry restoration work is underway. Tower Crane has been erected … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE- WEEKS OF MAY 2 AND 9 2022