DOMINO CONSTRUCTION UPDATE- WEEKS OF DECEMBER 26 AND JANUARY 2
Tower Crane has been erected and is active on a daily basis. Concrete superstructure and Steel Erection is complete at the Refinery. Exterior steel shoring towers have begun removal now that new steel is in place. Exterior masonry repairs are complete. Site … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE- WEEKS OF DECEMBER 26 AND JANUARY 2