DOMINO CONSTRUCTION UPDATE- WEEKS OF MAY 12 AND MAY 19
Initial excavation has commenced at Site B, with soil removal underway. The site is fenced off on all streets. All sites at Domino, with the exception of site B, are now completed or have interior work only remaining. Construction of … Continue reading