DOMINO CONSTRUCTION UPDATE: Weeks of December 30th 2019 and January 6th, 2020
At Site A the ground floor through 42nd floor slabs are complete. The bulkheads for the building are complete. MEP trades will continue fit out work in the commercial leg and the residential bridge. Precast Facade erection is complete, except … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE: Weeks of December 30th 2019 and January 6th, 2020