DOMINO CONSTRUCTION UPDATE: Weeks of December 24th and December 31st, 2018
At Site A the ground floor through 22th floor commercial and 28th floor Residential slabs are complete. Utility work in the street on Kent avenue is mostly complete with gas work wrapping up in the spring. MEP trades will continue … Continue reading