DOMINO CONSTRUCTION UPDATE: Weeks of December 24th and December 31st, 2018

At Site A the ground floor through 22th floor commercial and 28th floor Residential slabs are complete. Utility work in the street on Kent avenue  is mostly complete with gas work wrapping up in the spring. MEP trades will continue their overhead and in deck work. Precast Facade erection has begun on a second shift and will end prior to 10pm every evening. The facade is wrapping the building from bottom up. The precast planks should be installed and grouting, rebar and formwork for the connecting beams and slabs will begin. The site will be closed 12/24,12/25, 12/31 & 1/1.

The Refinery shoring work has begun. This will consist of steel structures on the exterior to brace the existing brick façade during demolition.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week