DOMINO CONSTRUCTION UPDATE:Week of March 2nd, 2015 and March 9th, 2015
Soot removal and asbestos abatement are ongoing inside the Boiler House stacks. Mechanical demolition will resume in the next 2 weeks. Preparations for interior hand demolition of The Refinery building are ongoing. A crane was installed on the north side of … Continue reading