DOMINO CONSTRUCTION UPDATE- WEEKS OF APRIL 3 AND APRIL 10

Tower Cranes have been erected and are active daily at both Site D and the Refinery.  Concrete superstructure and Steel Erection is complete at the Refinery, all Exterior steel shoring towers have been removed, and all façade masonry work is complete. Interior construction of the Refinery is underway. Site B is fenced off and is used for refinery construction staging. A separate portion of site B is accessible off river street containing Domino Park bathrooms and staffing/operations. Construction of Domino Park, Site E and Site A is complete.  Public entrances to Domino Park are on Grand St, South 1st St, and South 5th St. Sites C and D excavation and foundation work is complete. Site D superstructure has commenced, and site C cellar is under construction.

Posted in Construction Updates | Comments Off on DOMINO CONSTRUCTION UPDATE- WEEKS OF APRIL 3 AND APRIL 10