DOMINO SUGAR FACTORY CONSTRUCTION UPDATE – Weeks of September 23, 2013 and September 30, 2013

In an effort to keep the public aware of upcoming construction activities, Two Trees Management will provide updates every two weeks.

Please note: the exact scope and nature of the activities are subject to change based upon field conditions.

If you have any questions, please feel free to contact us at Domino@twotrees-dumbo.com or call at 718-384-9742.

Weeks covering September 23, 2013 and September 30, 2013

Asbestos Abatement

  • The relevant abatement is now complete at the site.

Demolition

  • Demolition contractors are installing a high-quality construction noise barrier at the perimeter of the entire site.
  • The demolition permit for Building 28 at the corner of Kent Ave and Grand Street (Phase 1) has been issued and demolition work will commence on/about September 26th and is expected to take approximately 10 weeks.
  • A third party construction monitor/ reporter has been hired and approved by Department of City Planning to oversee and certify the implementation of the specified environmental mitigation measures.

Traffic

  • A traffic plan showing all proposed alterations to land, street and sidewalk was been submitted and approved by Department of Transportation and Bikes Department.
  • The sidewalk, bike lane and street will be redirected according to those approved plans.

For questions, neighbors are encouraged to communicate via email at Domino@twotrees-dumbo.com.