In an effort to keep the public aware of upcoming construction activities, Two Trees Management will provide updates every two weeks.
Please note: the exact scope and nature of the activities are subject to change based upon field conditions.
If you have any questions, please feel free to contact us at Domino@twotrees-dumbo.com or call at 718-384-9742.
Weeks covering October 7, 2013 and October 14, 2013
Asbestos Abatement
- The relevant abatement was completed at the site in September.
Demolition
- Demolition contractors will complete the installation of a high-quality construction noise barrier at the perimeter of the entire site.
- A third party construction monitor/ reporter approved by Department of City Planning is in place to oversee and certify the implementation of the specified environmental mitigation measures.
- The demolition permit for Building 28 at the corner of Kent Ave and Grand Street (Phase 1) has been issued and demolition work commenced the week of September 30.
- Building 28 is expected to be demolished by October 7th. In the coming weeks, the debris will be sorted and removed from the site in accordance with our City-approved pre-construction plans.
Traffic
- A traffic plan showing all proposed alterations to land, street and sidewalk was been submitted and approved by Department of Transportation and Bikes Department.
- The sidewalk, bike lane and street have been redirected according to those approved plans.
For questions, neighbors are encouraged to communicate via email at Domino@twotrees-dumbo.com.