DOMINO CONSTRUCTION UPDATE:Week of July 28, 2014 and August 4, 2014
The Boiler House is undergoing Phase III mechanical demolition work. Machinery demolished and sorted metal on the north side of the Boiler House. On the south side of the Boiler House, workers aided by basket cranes flame cut steel from … Continue reading
Posted in Construction Updates