Sorting, grading, and cleaning activities are ongoing at the Raw Sugar Warehouse. Mechanical demolition of the Boiler House continues – workers were demolishing the building’s exterior bin structure. Hand demolition is ongoing at Building 16. Workers aided by a man-lift break brick away from the exterior at the top of the building.
-