Mechanical demolition of the Building 16 tower has been completed. Demolition is currently paused at the Boiler House while asbestos abatement activities are underway inside the stacks. Sorting and grading activities are ongoing throughout the Site. Support beams were installed on several structural steel beams at the Raw Sugar Warehouse as additional support.
-