Mobilization for construction has begun at “Site E”. Temporary orange barriers were installed along South 3rd and South 4th Streets. Temporary parking signs are currently posted until official signage is received from the DOT. Soot removal and asbestos abatement are ongoing inside the Boiler House stacks. Mechanical demolition will resume in the next 2 weeks.
-
Recent Posts
- DOMINO CONSTRUCTION UPDATE- WEEKS OF DECEMBER 26 AND JANUARY 2
- DOMINO CONSTRUCTION UPDATE- WEEKS OF DECEMBER 12 AND DECEMBER 19
- DOMINO CONSTRUCTION UPDATE- WEEKS OF NOVEMBER 28 AND DECEMBER 5
- DOMINO CONSTRUCTION UPDATE- WEEKS OF NOVEMBER 14 AND NOVEMBER 21
- DOMINO CONSTRUCTION UPDATE- WEEKS OF OCTOBER 31 AND NOVEMBER 7