DOMINO CONSTRUCTION UPDATE:Week of April 13th, 2015 and April 20th, 2015
Hand cutting of steel beams is ongoing to remove the standing skeleton of the boiler house building. Hand demolition in The Refinery building continues. R. Baker completed the removal the Domino Sugar cranes along the East River and is completely … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE:Week of April 13th, 2015 and April 20th, 2015