-
Recent Posts
- DOMINO CONSTRUCTION UPDATE- WEEKS OF NOVEMBER 9 AND NOVEMBER 16
- DOMINO CONSTRUCTION UPDATE- WEEKS OF OCTOBER 26 AND NOVEMBER 2
- DOMINO CONSTRUCTION UPDATE- WEEKS OF OCTOBER 12 AND OCTOBER 19
- DOMINO CONSTRUCTION UPDATE- WEEKS OF SEPTEMBER 28 AND OCTOBER 5
- DOMINO CONSTRUCTION UPDATE- WEEKS OF SEPTEMBER 14 AND SEPTEMBER 21
Daily Archives: May 26, 2015
DOMINO CONSTRUCTION UPDATE:Week of May 11th, 2015 and May 18th, 2015
Hand demolition of steel beams is ongoing to remove the standing skeleton of the boiler house building, half of which has been completed. Hand demolition continues in The Refinery building. Three (3) test-piles are installed on the Site. Fencing was installed … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE:Week of May 11th, 2015 and May 18th, 2015