DOMINO CONSTRUCTION UPDATE:Week of May 11th, 2015 and May 18th, 2015
Hand demolition of steel beams is ongoing to remove the standing skeleton of the boiler house building, half of which has been completed. Hand demolition continues in The Refinery building. Three (3) test-piles are installed on the Site. Fencing was installed … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE:Week of May 11th, 2015 and May 18th, 2015