DOMINO CONSTRUCTION UPDATE:Week of July 20th, 2015 and July 27th, 2015

Hand demolition in The Refinery building continues. The removal of the bulkhead concrete decking on the north end of the Site is continuing, work is progressing to the south. The public park located on Site C is open 6 days a week. A geotechnical drilling company was on site performing 20 soil borings around the Refinery and Site B.  At Site E excavation, load out, shoring and support of excavation work is occurring.

.