Hand demolition continues in The Refinery Building and loading out material stockpiled west of the Refinery building. The removal of the bulkhead concrete decking on the north end of the Site continues. Construction of the new park on Site C is complete. At Site E excavation, shoring and support of excavation work are ongoing.
-