Hand demolition continues in The Refinery building. The removal of the bulkhead concrete decking on the south end of the Site is ongoing. Thhey are removing metal piers from the River. aq concrete cutting company is on site to assist with demolition of the concrete deck. The public park located on Site C is open 6 days a week.
At Site E excavation is completed. underground utilities are underway. foundation concrete has also begun.