DOMINO CONSTRUCTION UPDATE:Week of January 25th, 2015 and February 1st, 2015

Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is ongoing. They are continuing to remove metal piers from the River.  The public park located on Site C is open 6 days a week.

At Site E superstructure concrete has begun and the first section of slab had been poured. All MEP trades have mobilized and have begun deck work.