DOMINO CONSTRUCTION UPDATE:Week of January 11th, 2015 and January 18th, 2015

Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is ongoing. they are continuing to remove metal piers from the River.  The public park located on Site C is open 6 days a week.

At Site E underground utilities in conjunction with foundation wall shot-crete work is Completed. Superstructure concrete is beginning imminently and all MEP trades are onboard and will mobilize shortly as well.