DOMINO CONSTRUCTION UPDATE:Week of September 5th, 2016 and September 12th, 2016

Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is complete. New piers are being installed in the east river to support the future bulkhead decking. Piers are being cut to final heights and pile caps are being delivered & installed. The new sea wall is partially installed. The public park located on Site C is open 6 days a week.

At Site E, superstructure concrete is underway and sections of the North and South tower deck and supporting columns are being poured daily. Concrete is on schedule to top out by the end of September. All MEP trades are continuing deck work and coordination efforts. installation of CMU, exterior & interior framing and MEP work is ongoing.