DOMINO CONSTRUCTION UPDATE: Week of February 6th, 2017 and February 13th, 2017

Creation of Domino Park is underway! Construction of our layout has begun, including earthwork and the marine platform deck. By the 2nd week of February our precast bulkhead work will be complete. Relocation of the site artifacts will begin in the coming weeks.

The removal of the bulkhead concrete decking on the river front is complete. The new sea wall is near completely installed. The public park located on Site C is open 6 days a week.

At Site E, superstructure concrete is COMPLETE. All MEP trades are doing riser and horizontal work. Installation of CMU, exterior & interior framing and MEP work is ongoing. Exterior walls are being clad and waterproofed using the mast climber’s onsite. Mechanical rooms are being built out.