Construction of the Domino Park is ongoing, including earthwork and utility work. Our bulkhead piers and deck is complete. Layout and construction of CMU planter walls and the western perimeter wall has begun. Electrical, utility and plumbing work has begun. The elevated walk steel is nearly complete and painting of the artifacts has begun.
The public park located on Site C is open 6 days a week.
At Site E, All MEP trades are doing riser and horizontal work along with roughing and final installation. Installation of exterior & interior framing and MEP work is ongoing. Exterior walls are being clad and waterproofed using the mast climber’s onsite. Mechanical rooms are being built out and apartment fit out has begun.