- DOMINO CONSTRUCTION UPDATE- WEEKS OF NOVEMBER 9 AND NOVEMBER 16
- DOMINO CONSTRUCTION UPDATE- WEEKS OF OCTOBER 26 AND NOVEMBER 2
- DOMINO CONSTRUCTION UPDATE- WEEKS OF OCTOBER 12 AND OCTOBER 19
- DOMINO CONSTRUCTION UPDATE- WEEKS OF SEPTEMBER 28 AND OCTOBER 5
- DOMINO CONSTRUCTION UPDATE- WEEKS OF SEPTEMBER 14 AND SEPTEMBER 21
Daily Archives: July 21, 2017
DOMINO CONSTRUCTION UPDATE: Week of July 24th, 2017 and July 31st, 2017
Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Layout and construction of CMU planter walls and the western perimeter wall has begun. Electrical, Mechanical and plumbing work has begun. The elevated walk steel is complete and painting … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE: Week of July 24th, 2017 and July 31st, 2017