DOMINO CONSTRUCTION UPDATE: Week of November 13th, 2017 and November 20th, 2017
Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Construction of CMU planter walls is complete and the western perimeter wall is complete. Electrical, Mechanical and plumbing work is ongoing. The elevated walk steel is complete and painting … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE: Week of November 13th, 2017 and November 20th, 2017