Monthly Archives: January 2018

DOMINO CONSTRUCTION UPDATE: Week of January 22nd, 2018 and January 29th, 2018

At Site A Excavation and dewatering work is ongoing and SOE and pile driving is complete. Excavation and trucking of soil is complete and production piles along with tie back installation is complete. Foundation footings have been poured and are … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of January 8th, 2018 and January 15th, 2018

At Site A ¬†Excavation and dewatering work is ongoing and SOE and pile driving is complete. Excavation and trucking of soil is continuing daily and production piles along with tie back installation is complete. Foundation footings have been poured and … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of December 25th, 2017 and January 1st, 2018

At Site A ¬†Excavation and dewatering work is ongoing and SOE and pile driving is complete. Excavation and trucking of soil is continuing daily and production piles along with tie back installation has begun. Foundation footings have been poured and … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of December 11th, 2017 and December 18th, 2017

At Site A ¬†Excavation, SOE, pile driving and dewatering work is ongoing. Excavation and trucking of soil is continuing daily and production piles along with tie back installation has begun. Foundation footings have been poured and are continuing to be … Continue reading

Posted in Construction Updates