-
Recent Posts
- DOMINO CONSTRUCTION UPDATE- WEEKS OF NOVEMBER 9 AND NOVEMBER 16
- DOMINO CONSTRUCTION UPDATE- WEEKS OF OCTOBER 26 AND NOVEMBER 2
- DOMINO CONSTRUCTION UPDATE- WEEKS OF OCTOBER 12 AND OCTOBER 19
- DOMINO CONSTRUCTION UPDATE- WEEKS OF SEPTEMBER 28 AND OCTOBER 5
- DOMINO CONSTRUCTION UPDATE- WEEKS OF SEPTEMBER 14 AND SEPTEMBER 21
Monthly Archives: January 2018
DOMINO CONSTRUCTION UPDATE: Week of January 22nd, 2018 and January 29th, 2018
At Site A Excavation and dewatering work is ongoing and SOE and pile driving is complete. Excavation and trucking of soil is complete and production piles along with tie back installation is complete. Foundation footings have been poured and are … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE: Week of January 22nd, 2018 and January 29th, 2018