-
Recent Posts
- DOMINO CONSTRUCTION UPDATE- WEEKS OF FEBRUARY 16 AND FEBRUARY 23
- DOMINO CONSTRUCTION UPDATE- WEEKS OF FEBRUARY 2 AND FEBRUARY 9
- DOMINO CONSTRUCTION UPDATE- WEEKS OF JANUARY 19 AND JANUARY 26
- DOMINO CONSTRUCTION UPDATE- WEEKS OF JANUARY 5 AND JANUARY 12
- DOMINO CONSTRUCTION UPDATE- WEEKS OF DECEMBER 22 AND DECEMBER 29
Monthly Archives: January 2018
DOMINO CONSTRUCTION UPDATE: Week of January 22nd, 2018 and January 29th, 2018
At Site A Excavation and dewatering work is ongoing and SOE and pile driving is complete. Excavation and trucking of soil is complete and production piles along with tie back installation is complete. Foundation footings have been poured and are … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE: Week of January 22nd, 2018 and January 29th, 2018