DOMINO CONSTRUCTION UPDATE: Week of February 19th, 2018 and February 26th, 2018

At Site A Excavation and dewatering work is ongoing and SOE and pile driving is complete.Some foundation footings have been poured and are continuing to be installed. Slab on grade and foundation walls for Site A will be installed over … Continue reading

Posted in Construction Updates | Comments Off on DOMINO CONSTRUCTION UPDATE: Week of February 19th, 2018 and February 26th, 2018