DOMINO CONSTRUCTION UPDATE: Week of January 22nd, 2018 and January 29th, 2018
At Site A Excavation and dewatering work is ongoing and SOE and pile driving is complete. Excavation and trucking of soil is complete and production piles along with tie back installation is complete. Foundation footings have been poured and are … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE: Week of January 22nd, 2018 and January 29th, 2018