-
Recent Posts
- DOMINO CONSTRUCTION UPDATE- WEEKS OF DECEMBER 8 AND DECEMBER 15
- DOMINO CONSTRUCTION UPDATE- WEEKS OF NOVEMBER 24 AND DECEMBER 1
- DOMINO CONSTRUCTION UPDATE- WEEKS OF NOVEMBER 10 AND NOVEMBER 17
- DOMINO CONSTRUCTION UPDATE- WEEKS OF OCTOBER 27 AND NOVEMBER 3
- DOMINO CONSTRUCTION UPDATE- WEEKS OF OCTOBER 13 AND OCTOBER 20
Monthly Archives: March 2018
DOMINO CONSTRUCTION UPDATE: Week of April 2nd, 2018 and April 9th, 2018
At Site A Excavation and dewatering work is Complete. Foundation footings have been poured. Slab on grade and foundation walls for Site A have begun and will be complete the week of 4/2. Underground plumbing and electric work is complete. … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE: Week of April 2nd, 2018 and April 9th, 2018