Daily Archives: March 30, 2018
DOMINO CONSTRUCTION UPDATE: Week of April 2nd, 2018 and April 9th, 2018
At Site A Excavation and dewatering work is Complete. Foundation footings have been poured. Slab on grade and foundation walls for Site A have begun and will be complete the week of 4/2. Underground plumbing and electric work is complete. … Continue reading