Monthly Archives: March 2018

DOMINO CONSTRUCTION UPDATE: Week of April 2nd, 2018 and April 9th, 2018

At Site A Excavation and dewatering work is Complete. Foundation footings have been poured. Slab on grade and foundation walls for Site A have begun and will be complete the week of 4/2. Underground plumbing and electric work is complete. … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of March 19th, 2018 and March 26th, 2018

At Site A Excavation and dewatering work is Complete. Some foundation footings have been poured and are continuing to be installed. Slab on grade and foundation walls for Site A have begun and will be complete in the next 2 … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of March 5th, 2018 and March 12th, 2018

At Site A Excavation and dewatering work is Complete. Some foundation footings have been poured and are continuing to be installed. Slab on grade and foundation walls for Site A have begun and will be complete in the next 2 … Continue reading

Posted in Construction Updates