DOMINO CONSTRUCTION UPDATE: Weeks of May 28th, June 4th, and June 11th, 2018
At Site A the ground floor and 2nd floor slab are complete. The 3rd floor concrete should be completed by 6/22. The Con-Ed vaults will be installed on Kent Ave this will reroute bike and pedestrian traffic for 3-4 weeks. … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE: Weeks of May 28th, June 4th, and June 11th, 2018