DOMINO CONSTRUCTION UPDATE: Weeks of May 28, June 4, & June 11.

At Site A the ground floor and 2nd floor slab are complete. The 3rd floor concrete should be completed by 6/22. The Con-Ed vaults will be installed on Kent Ave this will reroute bike and pedestrian traffic for 3-4 weeks. Sidewalk shed is erected. MEP trades have begun their overhead and in deck work. Curtainwall erection is set to begin in August.

Construction of the Domino Park is nearly complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street

The public park located on Site C is open 6 days a week.

Site E construction is complete.