DOMINO CONSTRUCTION UPDATE: Weeks of January 21st and January 28th, 2019
At Site A the ground floor through 22th floor commercial and 28th floor Residential slabs are complete. Framing and rebar above the bridge has begun. We will be pouring the 28th floor slab the week of the 28th and frame … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE: Weeks of January 21st and January 28th, 2019