DOMINO CONSTRUCTION UPDATE: Weeks of January 7th and January 14th, 2018

At Site A the ground floor through 22th floor commercial and 28th floor Residential slabs are complete. Framing and rebar above the bridge has begun. This is a lengthy process and are expecting to pour the slabs at the end … Continue reading

Posted in Construction Updates | Comments Off on DOMINO CONSTRUCTION UPDATE: Weeks of January 7th and January 14th, 2018